Work on the new Ardrossan Community Campus continues to make good progress, and we are pleased to share an update on activities completed over the past month.
What we've completed recently
Over the last four weeks, the project team has:
- finished installing floor slabs in the Central Wing
- continued foundation works in the Sports Wing
- made further progress on the new car parks
- advanced construction of the swimming pool floor and walls
- installed additional scaffolding, access platforms and safety handrails
- continued shaping and preparing the outdoor sports pitches
- progressed external wall construction in the Teaching Wing
- continued roofing works on the Teaching Wing
- started installing the building's external cladding
- begun fitting windows in the Teaching Wing
- started roofing works on the Central Wing
- commenced construction of the lift shafts
What to expect over the next four weeks
Our focus during the coming month will include:
- continuing foundation works in the Sports Wing
- further scaffolding and site safety improvements
- ongoing development of the sports pitches and car parking areas
- continued construction of the swimming pool structure
- further progress on external walls and roofing for the Teaching and Central Wings
- continuing installation of windows in the Teaching Wing
- ongoing installation of external cladding
- starting erection of the Sports Wing steel frame
- continuing work on lift shafts
- installing filtration pipework for the swimming pool
Please note that some foundation works will continue into November. In certain circumstances, this may require limited Saturday morning working to complete essential follow-up activities after concrete pours. Wherever possible, we will minimise Friday concrete pours to reduce the likelihood of weekend working, but this will depend on material availability and construction requirements.
We are also pleased to confirm that the concrete polishing works to both the teaching and central wings have now been completed. These works will not recommence until the Sports Wing structural steel frame has been erected. Thank you to local residents for your patience and understanding during this activity.
Working with the Community
Supporting the local community remains an important part of the project and we continue to work with local groups and organisations to create positive benefits during construction.
Macmillan Coffee Morning
The Ardrossan Community Campus project team and supply chain partners recently hosted a Macmillan Coffee Morning in support of Macmillan Cancer Support. Thanks to the generosity of everyone who attended, £220 was raised to help provide vital support and services for people affected by cancer.
Support for Ardrossan Winton Rovers
Morgan Sindall was proud to be the main sponsor of the Ardrossan Winton Rovers 2026 Golf Day at Ravenspark Golf Course. The event brought together local golfers, volunteers and organisations, helping to support the club and strengthen community connections across the Three Towns area.
For further information on project progress and community initiatives, please visit the dedicated project website.
Keeping in Touch
We appreciate that major construction projects can sometimes cause disruption, and we remain committed to keeping this to a minimum wherever possible.
We will continue to try and minimise disruption to all local residents/neighbours, but should you experience any issues, please contact Victoria Proven, Senior Site Manager on 07773 592674 or on 20CB10.ardrossancc@morgansindall.com.
Construction Working Hours
- Monday to Friday: 7.30am to 6pm
- Saturday: 8am to 1pm (only with prior Council approval)
- Deliveries: 8am to 6pm (scheduled and managed through the CLOCS system with timed delivery slots)
- Sunday working: Would only take place with prior Council approval and would be limited to quieter activities where appropriate.